When it was licensed in 1925, the 11.2 mile Borel Project was designed as a “Run of River” hydroelectric project which means the natural flow and elevation drop of a river are used to generate electricity. For Borel, water was taken from either the Kern River’s north fork or more recently, at the Lake Isabella Auxiliary Dam depending upon the water level of Lake Isabella. Water then travelled through the Borel Canal and into the Borel Powerhouse where 11 MW of power was steadily generated.
The Borel Hydroelectric Project is owned and operated by Southern California Edison (SCE).
In 2006, the Army Corps of Engineers began a dam safety modification study and determined that the dam didn’t meet earthquake safety standards. As a result, the Corps began a dam safety modification project. In 2017, the Corps began seismic safety modifications to the Auxiliary Dam which resulted in the condemnation of SCE’s canal conduit through the dam. The conduit through the dam was abandoned in place by filling it with concrete and rendering the Project nonfunctional. Because of that, SCE is preparing to file a license Surrender Application with the Federal EnerSy Regulatory Commission (FERC).
A Surrender Application is what SCE must file before the Federal Energy Regulatory Commission (FERC) will allow them to decommission the Borel Canal, Powerhouse and associated project features. FERC processes the Surrender Application to ensure that safety and environmental concerns are addressed.
To surrender a License, SCE will need to prepare an application that includes the following information: The reason for surrendering the license, a copy of the license and all amendments associated with the project. The application must address issues such as public safety, environmental resources, tribal and cultural resources and document the stakeholder consultation process. At the heart of the application is the decommissioning plan. This plan will provide the approach for removing project facilities and land restoration activities.
The Federal Energy Regulatory Commission (FERC) is a federal agency that regulates the interstate transmission of natural gas, oil, electricity and hydropower projects. They are responsible for issuing hydropower project initial licensing, relicensing and decommissioning.
Approval from Federal Energy Regulatory Commission to develop and operate a hydroelectric project for a specified period the of time.
Approximately 189 acres are owned by the federal government and 23 acres are privately held.
SCE submitted the application in May of 2023.
Yes. The Surrender Application is located in the section below and is also available through the FERC eLibrary.
Addressing potential public safety risks associated with the project facilities
Remediating any environmental, cultural, tribal, historic and socio-economic impacts associated with the existing project
Restoring public and private project lands to a satisfactory condition
Removing land easements and right of ways associated with project roads and facilities
There is no defined amount of time FERC takes to review applications. SCE is planning for the process to take between 2 to 5 years, but I could be longer. Once the review process is complete and FERC is satisfied with the contents within the application, they will provide their approval to begin the decommissioning process.
SCE will continue to maintain the Borel Canal and associated facilities as they are now until such time as decommissioning activities, such as permitting, start.
We don’t have an exact date at this time. We anticipate that construction along the canal could begin as early as 2027, but will likely be later.
The documents on this page have been filed with FERC as part of the Borel Hydroelectric Project Surrender Application process.
Volume I - Initial Statement – Download
Volume II - Decommissioning Plan – Download
Volume III - Applicant Prepared Draft Environmental Analysis – Download
Volume IV - Record of Consultation – Download